MODEL 7100 INSTALLATION MANUAL
Description Page
Residential & Medium Duty Commercial
Slide Gate Operator

CONTENTS
Safety Precautions
Applications
Pre-installation Checklist
Parts Identification
Pad Installation
Operator Installation
Chain Bracket Installation
Chain & Chain Bolt Installation
Chain Magnets Installation
Quick Release Operation
Control Board Connections
Control Board Adjustments
Warranty
SAFETY PRECAUTIONS
IMPORTANT: READ CAREFULLY BEFORE BEGINNING INSTALLATION
-
Read this installation manual completely prior to
installation.
-
Installation should be performed by a professional installer.
-
Required welding should be performed by a qualified welder.
-
Should electricity be required~ use a certified electrician only.
-
Any device that requires i20 Volts AC should be UL approved.
-
Review with the owner all safety concerns including:
-
Do not operate the gate unless area around gate is in full view.
-
Do not allow children or adults to "ride" on gate during
operation
-
Do not allow children to play in the gate area
-
Periodically test the obstruction sensitivity to assure safe and
proper operation. Do not test sensitivity by standing between the gate and the hinge or stop post.
-
Do not allow children to play with the gate controls.
-
The "CAUTION AUTOMATIC GATE" sign should be clearly
visible from both sides of the gate.
-
Always insure that the gate has closed securely before leaving
area.
-
Arrange with local fire and law enforcement for emergency
access.
-
Recommend safety devices such as loop detectors, edge switches,
and beam detectors when applicable.
-
Install control devices such as keypads far enough away (5 feet
or further) from any moving parts of the operator and. gate to prevent possible injury.
-
Always disconnect the battery or power source when making adjustments
or repairs to any part of the gate or operator.
-
All rollers should be covered to prevent injury.
Top
APPLICATIONS
The Apollo Model 7100 Slide Gate Operator is designed to
handle a slide gate up to 27 feet in total length (accommodates a 25 foot
drive). A professional fence or gate
dealer is recommended to assure proper installation Apollo Gate Operators are available only through qualified dealers with an outstanding
reputation in the fence and gate industry These dealers will be able to recommend the
proper equipment for particular applications Apollo Gate Operators are 12 Volt DC
(Direct Current) powered A 12 Volt marine type battery with connecting posts
located on the top is recommended There are several advantages with 12 Volt DC systems:
-
Low voltage virtually eliminates risk of electrical shock.
-
Battery powered operators provide up to 200 operations in the
event of power outages.
-
The battery may be recharged with a trickle charger or by solar
energy (eliminating the need for costly trenching to remote entrances).
If a trickle charger is used and a standard electrical outlet is
not readily available, a licensed electrician will be required for proper electrical hook
up.
The following table should be used as a guide for capacity of operation of operators
only, additional options may reduce the the daily usage. Please note that the charge
capability of solar panels will vary with different geographical locations.
Charging Methods for Average Daily Usage
| Model # |
Daily Usage -> |
1-15 |
16-30 |
31-60 |
61-120 |
121+ |
| 201 |
5 watt of solar panel w/battery |
X |
|
|
|
|
| (2) 201 |
10 watts of solar panel w/battery |
|
X |
|
|
|
| MSX20 |
20 watts of solar panel w/battery &
regulator SRX6 |
|
|
X |
|
|
| MSC40 |
40 watts of solar panel w/battery &
regulator SRX6 |
|
|
|
X |
|
| 404 |
1.5 amp automatic charger w/battery |
|
|
|
|
X |
| 406 |
10 amp automatic charger w/battery |
|
|
|
|
X |
Top
PRE-INSTALLATION CHECKLIST
The following checklist should be used before beginning installation:
Verify that the proper operator has been selected for this application.
Verify proper installation and operation of the gate.
- Are all rollers covered with a protective housing?
- Are the rollers serviceable?
- Does the gate roll free and level?
- Will the gate require a locking device?
- Is the main posts sturdy enough to handle the gate & operator?
Determine the general location of the operator, attachment points, and solar
panel (if used).
- Is there a suitable location for the operator?
- Can the solar panel (if used) be mounted in an unobstructed area facing
south (in the northern hemisphere)?
- Will additional solar panel cable be required?
- Is electricity available (if required)?
Consider safety and access options. Recommend if needed.
- Will there be children or animals in the area?
- Are safety loops, edge switches, or photo beam detectors required?
- How can the gate be opened in emergencies?
- How will visitors enter and exit?
- Will vehicles (and trailers) have sufficient room off roadway to operate any
control devices such as keypads?
Top
PARTS
IDENTIFICATION
Top
PAD
INSTALLATION
 |
|
 |
 |
|
The required depth of the pad will vary
from site to site. Normally, the pad should be at least 4"
above the surface and 18" below (Figure A & B). |
|
Conduit requirements should be considered
in the planning stage. If electrical power is required, a separate
conduit should be installed for electrical only. A certified
electrician should be consulted for the proper conduit material (Figure D
& E) |
 |
|
|
Note: Allow the concrete to
cure as per the directions on the bag. The mounting holes for the
operator should be drilled after the concrete has cured. |
Top
OPERATOR
INSTALLATION
Four 1(2 anchor bolts (not supplied) are recommended to mount the chassis The
holes should be drilled with a 1/2" concrete drill bit.
|
 |
STEP 1 Set the operator on the pad as shown. Align the sprockets 3 to 5 inches from the
inside surface of the gate.
STEP 2 Mark the four mounting holes on the pad.
STEP 3 Remove the operator and drill the holes according to the anchor bolt manufacturers instructions.
STEP 4 Replace the operator and fasten to the pad.
|
|

|
Top
CHAIN BRACKET INSTALLATION
STEP 1. Assemble chain bracket with 5/16" U-bolt &
hardware to each end of the gate as shown. Do not tighten at this time.
 |
 |
|
STEP 2. Align the left chain bracket slot
with the top teeth of the idler sprocket.
Idler Sprocket
Main Sprocket
STEP 3. Align the right chain bracket slot
with the bottom teeth of the main sprocket. |
 |
Top
CHAIN &
CHAIN BOLT INSTALLATION
STEP 1. Connect chain bolt to the chain bracket as
per Figure A & B on both ends of the gate.
 |
 |
 |
STEP 2. Attach the chain to the chain bolt
using the master chain link.
Note: A chain breaking tool may be
required to reduce the chain to the proper length. |
 |
TIP: If welding equipment is available,
tack weld the chain bracket to the gate on each end to prevent slippage. |
Top
CHAIN
MAGNETS INSTALLATION
-
Align each magnet with the corresponding switch on the
operator.
- Connect the battery and adjust the magnets for proper open &
close limits.
WARNING: Always disconnect battery prior to relocating the
magnet
TIP: If the gate automatically opens after the close
timer expires, reverse the red & black motor wires and reverse the
orange & white limit wires.
|
|
 |
|
 |
Top
QUICK
RELEASE OPERATION
Top
CONTROL BOARD
CONNECTIONS #635/636
|